Surrey Council Confident in Meeting Electric Vehicle Charging Infrastructure Goals Despite Grid Connection Delays
Surrey County Council remains confident about installing 2,000 public EV charge points by 2028 despite current infrastructure standing at just 375 units. Officials cite power connection delays as the primary challenge, with some projects waiting years for grid connections. UK Power Networks continues supporting local authorities’ electric charging strategies amid nationwide pressure.
Ambitious EV Infrastructure Targets
Surrey County Council maintains its target to install hundreds of new public on-street electric vehicle charge points remains “achievable” despite slower-than-expected progress, according to reports. The ambitious plan aims to deploy 2,000 charging points by February 2028 and expand to 2,500 by 2030, though current installation numbers stand at just 375 as of September, sources indicate.